Title - Doubling of Dindigul-Villupuram rail line to be ready by SeptemberPosted by : irmafia on May 16, 2013 - 06:00:09 AM |
|
|
The stage has been set for the inspection with completion of the track doubling work between Valadi and Kallakudi Palanganatham in the Tiruchi – Ariyalur broad gauge section. S K Mittal, Commissioner of Railway Safety, will conduct both trolley inspection and a speed trial run on the 25-km stretch from Valadi to Kallakudi Palanganatham on 17 May from the Kallakudi Palanganatham side. The stretch, with four major bridges, 80 minor bridges, 13 level crossings, and four stations, has been completed at a cost of Rs. 100 crore. |