Indian Railways News => Topic started by RailEnquiry Admin on May 08, 2017 - 10:01:22 AM


Title - Rail Vikas Nigam Limited in East coast railway to complete four projects in two years
Posted by : RailEnquiry Admin on May 08, 2017 - 10:01:22 AM

Following important projects will be completed by Rail Vikas Nigam Limited (RVNL) in the span of two years –

Haridaspur – Paradeep new Rail line -

  • Full line to be complete by June 2018
  • Track linking work to start from June-2017 this year from Haridaspur side.

Angul – Sukinda New Rail line

  • Full line to be complete by June-2019
  • Track linking work to start from Budhapank side by November, 2017.

Bhubaneswar new station -

Will be ready for commissioning by end of May-2017.

Jakhapura – Nayagarh Doubling work -

  • Basantpur-Naranpur by March-2018
  • Sitabinj-Basantpur by June-2018